Description
The concrete of the segment is poured and hardens. After that, the affected structural parts are activated.
Arguments
The basic arguments correspond to those of all tasks (cf. TCL Command TASK). The other arguments are to be entered in the form "key=value".
There are following other specific predefined arguments:
Key |
Value |
Dimension |
Meaning |
Dshrink |
dshday |
INT |
Start of drying shrinkage |
Scopes
TASKS/CONTAINER
Examples
TASKS BEGIN
#task taskname day1 duration assembly [SKIP] additional args
CONTAINER 1 LOCAL 7 "" "descr=Cantilever, Pier 1"
TASK TRAVELER 1 LOCAL 7 2 "traveler=TR" "side=0"
TASK INSTSEG 2 LOCAL 5 3
CONTAINER END
CONTAINER 1 LOCAL 7 "" "descr=Cantilever, Pier 1"
TASK TRAVELER 1 LOCAL 7 5 "traveler=TR" "side=1"
TASK INSTSEG 2 LOCAL 5 6
CONTAINER END
CONTAINER 1 LOCAL 7 "" "descr=Cantilever, Pier 2"
TASK TRAVELER 1 LOCAL 7 8 "traveler=TR" "side=1"
TASK INSTSEG 2 LOCAL 5 9
CONTAINER END
CONTAINER 1 LOCAL 7 "" "descr=Cantilever, Pier 2"
TASK TRAVELER 1 LOCAL 7 11 "traveler=TR" "side=0"
TASK INSTSEG 2 LOCAL 5 12
CONTAINER END
TASKS END
The first steps of the cantilever construction above piers 1 and 2 are carried out on the left and right sides. The preprocessor will translate the information into the corresponding calculation tasks. In the process, the forces are applied by the traveler and removed again. The new segments are concreted and activated.
|