TCL Command TASK

Inhalt

Index

Under construction.

Term

TASK arg1 arg2 arg3 arg4 arg5 arg6 ....

Description

Each task has up to 6 predefined arguments, which are described here. The arguments specific to a task are described in the respective subchapter.

In addition, a user-defined task can be freely entered in the schedule, with the name of the task and its additional arguments. These tasks are only administered.

Arguments

Minimum quantity: 2

arg1

Value

Dimension

Meaning

taskname

TEXT

Predefined or user-defined name of the task

arg2

Value

Dimension

Meaning

day1

INT

Number of the day depending on arg2; If the task is in a final phase (start day of the phase = FINAL), then the start days of all tasks of the phase are to be specified with day1 = 1 and arg3 = LOCAL.

yyyymmdd

INT

Calendar day (arg3 = DATE)

arg3

Value

Dimension

Meaning

LOCAL

KEYWORD

The entered day refers to the parent start day.

LOCALUP

KEYWORD

The entered day refers to the parent start day of level 2. Subtasks of a container refer to the start day of the phase. For tasks outside a container applies: GLOBAL = LOCALUP.

GLOBAL

KEYWORD

The entered day is defined globally in the build plan.

DATE

KEYWORD

The entered day is a calendar date. Calendar days are only useful when using the construction plan for a real construction site organization.

arg4

Value

Dimension

Meaning

dur

INT

Dauer; Einige Aufgaben erfordern die Angabe der Dauer, so zum Beispiel das Betonieren (CONCRETE).

arg5

Value

Dimension

Meaning

iasm

INT

Number of the assembly to which the task is applied.

arg6, arg7, …

Value

Dimension

Meaning

SKIP

KEYWORD

The task is ignored during analysis.

"key=value"

TEXT

All other arguments depend on the type of task and are described in the corresponding subchapters. Those arguments are to be used as "key-value" inputs of the form "key=value”.

"descr=text"

TEXT

Descriptive text

Scopes

TASKS, CONTAINER, LOADCASE, FATIGUE

Examples

#task taskname day1 duration assembly [SKIP] additional args

TASK CONCRETE 1 LOCAL 14 1 "Dshrink=0" "descr=Pour and harden"

Concreting of a structural part defined by Assembly 1 takes place on day 1 of the phase and lasts 14 days.