Description
The concrete is poured and hardens. After that, the affected structural parts are activated.
Arguments
The basic arguments correspond to those of all tasks (cf. TCL Command TASK). The other arguments are to be entered in the form "key=value".
There are following other specific predefined arguments:
Key |
Value |
Dimension |
Meaning |
Dshrink |
dshday |
INT |
Start of drying shrinkage |
Scopes
TASKS, CONTAINER
Examples
TASK CONCRETE 1 LOCAL 21 1 "Dshrink=0"
The concreting of the structural members of assembly 1 starts at day 1 and takes 21 days. The start of drying shrinkage is immediate.
|