Description
Pouring of concrete can be done as a single task POUR or by the macro task CONCRETE.
Arguments
The basic arguments correspond to those of all tasks (cf. TCL Command TASK). There are no other arguments.
Scopes
TASKS, CONTAINER
Examples
TASK POUR 1 LOCAL 5 2 "descr=Pouring"
The structural members of assembly 2 are poured at day 1 . The process takes 5 days.
|