TCL Command DAYBEGIN

Inhalt

Index

Syntax

DAYBEGIN arg1

Description

The start day of the schedule is 1 if the schedule is for static analysis. The dependence of the calculation on a calendar day does not make sense for this case. However, if the construction plan is to be used for real construction, then a calendar day can be used as the start day.

The day is the smallest unit of the Allplan Bridge construction plan.

Arguments

Minimum quantity: 1

arg1

Value

Dimension

Meaning

1

INT

Day 1 of calculation

yyyymmdd

INT

Calendar day, consisting of year, month and day

Scopes

CONSTRUCTION

Examples

DAYBEGIN 1

The calculation starts with day 1.

DAYBEGIN 20230329

The construction begins on 29. March 2023.