Syntax
DAYBEGIN arg1
Description
The start day of the schedule is 1 if the schedule is for static analysis. The dependence of the calculation on a calendar day does not make sense for this case. However, if the construction plan is to be used for real construction, then a calendar day can be used as the start day.
The day is the smallest unit of the Allplan Bridge construction plan.
Arguments
Minimum quantity: 1
arg1
Value |
Dimension |
Meaning |
1 |
INT |
Day 1 of calculation |
yyyymmdd |
INT |
Calendar day, consisting of year, month and day |
Scopes
CONSTRUCTION
Examples
DAYBEGIN 1
The calculation starts with day 1.
DAYBEGIN 20230329
The construction begins on 29. March 2023.
|